A professional services firm
Twenty-two thousand square feet, and a date that could not move.
The lease on the existing building expired on a fixed date. A long-lead item on the M&E package threatened the programme in week three.
We resequenced the finishing trades around the late package and brought two of them forward, working an agreed extended shift for a fortnight rather than across the whole job.
Handed over four days before the lease expiry with a snag list under fifty items.
Results
How we work
Four stages, and you will always know which one you are in.
01
A conversation and a site visit. We will say early if the scheme and the budget are not going to meet.
02
Buildability, cost plan, programme and procurement — the work that decides how the rest goes.
03
Weekly progress reporting, a named site manager, and no surprises on the valuation.
04
Commissioning, O&M manuals, a snag list closed out, and a defects period we answer.
Send us the drawings, or just tell us what you are hoping to do. We will come back with an honest view of programme and cost.
Enquire about a project